Menu
Represented public owner in pursuing claims against and defending claims of terminated construction contractor on $19 million public works contract. Litigation included exchanging tens of thousands of documents, 42 percipient depositions, 24 days of hearing, 21 percipient witnesses, over 750 exhibits, and more than 200 pages of post-hearing briefing. Our client was found to be prevailing party and was awarded substantial damages.